Resorts World, NEC Birmingham

Installation of 5 star hotel plantroom for T&S:

A medium sized plantroom, 10″ low loss header feeding x2 LTHW plate heat exchangers then pumped to hotel and spa. X1 CHW Plate Heat exchanger to feed CHW fancoils in hotel.

Pipework victaulic and prefabricated welded pipework.

X3 HWS CHLORIFIERS for the DHWS for hotel piped in brazed copper and press fit copper.

Contract completed and tested in 4 weeks, we have ongoing works now until contract completes, anticipated July 15th.

Working commenced on roof chillers; aircoolers and pipework distribution on various floors.

Contract Duration = Ongoing.